Home interior timeline: from design sign-off to handover in 45 days
A week-by-week look at how a 2 or 3 BHK goes from first conversation to handover — and why factory production in parallel with site work makes 45 days possible.
"How long will it take?" is the second question almost every family asks us, right after "How much will it cost?" For many households in Delhi NCR the answer matters as much as the budget — every extra month can mean paying rent and a home loan EMI at the same time.
This guide walks through a typical LIVSTYL project timeline for a 2 or 3 BHK, week by week, from the first conversation to the day you get the keys back. The headline: about 45 days from design sign-off to handover, with design and approvals usually taking two to three weeks before that.
Key takeaways
- The 45-day clock starts at design sign-off, not at the first meeting. Quick, clear decisions in the design stage shorten the overall timeline.
- Factory production and on-site civil work run in parallel — that is what makes 45 days possible.
- Payments are tied to milestones: 10% at booking, 50% at production start, 35% before installation and 5% at handover.
- Society approvals, late changes and delayed possession are the most common reasons timelines slip.
The timeline at a glance
| Stage | Typical duration | What happens | Payment milestone |
|---|---|---|---|
| Consultation | Day 1 | Free conversation, site visit and measurements | — |
| Design | 1–2 weeks | Layouts, mood board, material samples, electrical plan | — |
| 3D & approval | About 1 week | Photoreal 3D renders, revisions, itemised fixed quote | 10% at booking |
| Production & site work | 20–25 days | Factory manufacturing; civil, electrical and ceiling work on site | 50% at production start |
| Installation & finishing | 7–12 days | Modular installation, countertops, painting, lighting, 146-point quality check | 35% before installation |
| Handover | Around day 45 after sign-off | Deep clean, styling, walk-through, warranty documents | 5% at handover |
Typical for 2–3 BHK apartments in Delhi NCR. Villas, large homes and Luxury projects usually take 60–90 days or more.
Before the clock starts: consultation and design
Day 1: consultation
A designer meets you at home, online or at our studio in Faridabad. We listen first — how your family uses each room, what you own, what frustrates you about your current home, your style and your budget. For homes anywhere in Delhi NCR, a designer visits to measure and photograph the site.
Bring: your floor plan, possession date, a few photos you love and a list of furniture you are keeping.
Weeks 1–2: design development
- 2D furniture layouts for every room.
- A mood board and materials palette.
- Physical samples of laminates, veneers, countertops and fabrics.
- An electrical and lighting plan — switch positions, TV points, AC points, lights.
This is the cheapest stage to change your mind. Moving a wardrobe on a drawing costs nothing; moving it after production costs time and money.
Week 3: 3D visualisation and approval
Approved layouts become photoreal 3D renders, including how rooms look with lighting at night. After the revision rounds included in your package, you receive a fixed, itemised quote. Once you approve the design and pay the 10% booking amount, the price is locked and the 45-day clock starts.
Days 1–25: production and site work in parallel
In the factory
- Final site re-measurement to the millimetre.
- Approved designs converted into CNC cutting lists.
- Panels cut, edge-banded and drilled by machine.
- Units pre-assembled and quality-checked before dispatch.
On site
- Protection of floors, windows and fittings.
- Civil work — breaking, plastering, tiling where needed.
- Electrical wiring, conduits and new points.
- Plumbing changes in kitchen and bathrooms.
- False ceilings and the first coats of paint.
You receive weekly photo updates and can visit the site any time with your project manager.
Days 26–40: installation and finishing
- Modular units arrive packed and labelled room by room.
- Kitchens, wardrobes and units are installed by our own trained crews.
- Countertops are templated and fitted; appliances are installed.
- Final coats of paint, lighting fixtures and wallpaper or accent finishes.
- Curtains, blinds and soft furnishings.
Every room is checked against the 3D design, and we ask you to approve each room as it is completed.
Days 41–45: quality check and handover
- 146-point quality check covering alignment, hardware, finishes, electrical and cleanliness.
- Snag list closure — every issue fixed before handover.
- Deep cleaning and styling.
- A walk-through with your designer, care instructions for each finish, warranty certificate and appliance manuals.
All modular work carries a 10-year warranty, and civil, electrical and paint work carry a 1-year workmanship warranty. Read the details on our warranty policy page.
Your role at each stage
A 45-day schedule is a shared effort. Here is what helps most from your side:
- During design: share honest feedback early, visit the material library once, and confirm your appliance models — the hob, chimney, oven and fridge sizes decide kitchen cut-outs.
- Before sign-off: read the itemised quote line by line and walk through each 3D render. Our guide on reading an interior quotation lists what to check.
- During production: keep the society paperwork moving and make sure the site has power and water for the team.
- During installation: approve each room as it is completed so small fixes happen while the team is still on site.
- At handover: walk through every room with the snag list, test every drawer, switch and tap, and keep the warranty documents somewhere safe.
Families who make decisions within a few days at each step usually finish the design stage in under three weeks.
What can delay the timeline — and how to avoid it
| Common cause | How to avoid it |
|---|---|
| Late design changes | Take time during design; review 3D renders carefully before sign-off |
| Society approvals and work-hour limits | Apply for the interior work NOC early; we help prepare paperwork |
| Possession or handover delays from the builder | Design before possession; start production once dates are confirmed |
| Site issues (seepage, uneven floors) | Inspect early and fix civil issues before modular installation |
| Client-supplied items arriving late | Order appliances, tiles or lights you are buying yourself in good time |
| Festive season and monsoon | Allow a small buffer during peak periods |
How to move in faster
The quickest projects start well before possession. With your builder's floor plan, design and 3D can be completed before you get the keys, so site work begins in week one of possession. Our 90-day pre-possession checklist walks through the steps.
Want to see how each stage works in more detail? Visit our process page, estimate your budget with the cost calculator, or book a free consultation to get a dated schedule for your home.
Frequently asked questions
Does the 45 days include the design stage?
No. The 45-day average is counted from design sign-off. Design and 3D approval usually take two to three weeks before that, depending on how quickly decisions are made.
Can I visit the site during work?
Yes. You can visit any time, and your project manager shares weekly photo updates and walks you through progress.
What if the project takes longer than planned?
Your schedule is shared at sign-off and updated weekly. If something changes — for example, a society restriction or a design change — your project manager explains the impact on dates before work continues.
Can I stay in the flat while work is going on?
For a full-home project it is not practical — there is dust, noise and furniture being installed in every room. For a single-room project such as a kitchen or one bedroom, many families stay on, and the team plans the work to keep the rest of the home usable.
Is 45 days realistic for a 3 BHK?
For most 2 and 3 BHK apartments, yes, about 45 days after design sign-off. Larger homes, villas and Luxury projects with bespoke elements typically need 60–90 days.